Oil and gas plant upgrades can run over budget and behind schedule when site conditions differ from the drawings, inspections uncover unexpected repairs or critical work cannot fit into a fixed shutdown window. These are common risks in brownfield projects, where teams must install and test modifications within an existing facility while working around production commitments.
A single discrepancy can affect both cost and schedule. If a prefabricated pipe spool will not fit, the team may need new measurements, revised drawings and replacement fabrication. Even when the direct repair cost is modest, the delay can hold up testing and push back the unit’s return to service.
Why upgrading an existing oil and gas plant is complex
A brownfield project modifies, upgrades or expands an existing asset. Examples include connecting a new compressor to a gas plant, replacing an obsolete control system or increasing the throughput of a separation train. Greenfield projects develop a new facility. For an upgrade, the design must also account for installed equipment, existing utilities, access restrictions and the condition of the systems it connects to.
The International Energy Agency found that nearly 90% of annual upstream oil and gas investment since 2019 had gone towards offsetting production declines. That figure covers upstream spending such as work on wells and drilling alongside investment in surface facilities. For operators planning upgrades, the practical challenge is to maintain production while making changes that support continued operation. www.iea.org IEA analysis of oil and gas field decline rates
Three causes of plant upgrade cost overruns and delays
1. Drawings and site conditions do not match
Piping and instrumentation diagrams (P&IDs), layout drawings and equipment records may miss changes made during previous repairs or modifications. A proposed route can look clear on a drawing yet clash with a cable tray or structural support. If the discrepancy is found after fabrication, the team may have to redesign, remake and reinstall components within the same shutdown window.
Before issuing drawings for fabrication, verify the dimensions, clearances and connection points that would be most costly to correct later. PetroKnowledge’s Brownfield Modifications & Tie-In Engineering training course examines how to investigate these engineering uncertainties and assess whether a proposed tie-in is feasible.
2. Inspections uncover work outside the original scope
The condition of some components becomes clear only after equipment is taken out of service and made available for inspection. A damaged flange or a section of pipe that needs replacement can create an immediate need for materials, specialist labour and engineering review. The schedule impact depends on whether the extra work blocks a tie-in, a test or another activity required for restart.
Before the shutdown, agree who assesses new findings, who approves additional work and how changes are reflected in the schedule. Set aside contingency for plausible discoveries and check lead times for the spares or services they are likely to require.
3. Several activities depend on the same shutdown window
Construction, maintenance and inspection crews may need access to the same unit or share lifting equipment and specialist labour. Late access to one work area can delay a series of dependent tasks. Testing, reinstatement and handover also need time within the window, so mechanical completion is only one milestone on the way to restart.
Build the schedule backwards from the conditions required for a safe return to service. For teams responsible for planning and coordinating outages, the Turnaround Works for Onshore and Offshore Facilities training course covers preparation, project control and execution.
How to keep an oil and gas plant upgrade on track
- Check the site assumptions that can change the design. Prioritise uncertain tie-in locations, equipment clearances and installation access. Use walkdowns, measurements or laser scanning where the information will affect a design or construction decision.
- Involve operations and maintenance before finalising scope. Ask site teams to flag equipment history, access limits and operating conditions that drawings may omit. Confirm which activities can take place during normal operation and which require a shutdown.
- Agree how late changes will be reviewed. Set a scope-freeze date, assign approval authority and assess proposed additions against cost, resources and restart readiness. Record which items can be deferred and which must be resolved in the current window.
- Review potential conflicts between concurrent activities. Bring construction, operations and maintenance teams together to identify simultaneous operations (SIMOPS), temporary arrangements and shared resources. Address changes through the site’s management-of-change process.
- Track the work that controls the restart date. Monitor access, materials, testing and handover alongside installation progress. Review how any newly discovered work affects these dependencies before committing to a revised completion date.
Teams that need to manage scope, interfaces and schedule across an operating facility can develop those skills through PetroKnowledge’s Project Management for Brownfield Oil & Gas Projects training course.
UAE example of expanding an operating gas plant at Habshan
In June 2025, ADNOC Gas announced approximately US$5 billion in contract awards for the first phase of its Rich Gas Development project. The work was intended to expand key processing units at four existing facilities. Wood received the US$2.8 billion engineering, procurement and construction management package for Habshan. ADNOC Gas project announcement
Wood said its scope included upgrades to existing gas processing facilities and pipelines, alongside new installations. It planned to carry out the work while the facilities remained operational to sustain gas supply. For projects of this kind, production continuity is a requirement that influences how construction and commissioning are planned.
How emissions and digital upgrades affect the schedule
A compressor electrification project may depend on additional power capacity and a shutdown for connections. A flare-reduction retrofit may require piping tie-ins or changes to the control system. A digital twin used to plan modifications depends on reliable information about equipment and layout. Include these dependencies in the wider plant schedule early so teams can see where surveys, access and shutdown work overlap.
For engineers, project managers and operations teams preparing to modify an existing facility, PetroKnowledge’s Brownfield Engineering Training Courses cover facility assessment, engineering modifications and how to integrate new equipment with operating assets.
Frequently asked questions
-
Why can a small plant modification cause a long delay?
A small modification can sit on the critical path if it must be completed before testing or restart. An incorrect dimension, late valve delivery or unavailable work area can then delay several activities that depend on it.
-
What is discovered work during a shutdown?
Discovered work is additional work identified after inspection or access reveals a condition that could not be confirmed during planning. The team assesses whether it must be completed before restart and what it means for cost, resources and schedule.
-
What is the difference between a plant upgrade and a turnaround?
A plant upgrade changes the facility or its equipment. A turnaround is a planned shutdown for inspection, maintenance and other work that requires the equipment to be out of service. An upgrade may use that window to carry out tie-ins or other shutdown-dependent work.
-
What is debottlenecking in oil and gas?
Debottlenecking removes or eases the constraint limiting a plant’s throughput. An upgrade might address a pump, compressor, exchanger or utility. The engineering review should also establish where the next constraint is likely to occur once capacity changes.